Standby power control design

Skyward prepared the control design and commissioning documentation for a standby-power systems upgrade at Hastings Hospital.

Redundancy built into the controls

The design includes a redundant power-system control arrangement, with a watchdog function to switch to a secondary control system. Modbus integration connects smart air circuit breakers and moulded-case circuit breakers with the wider power-system controls and SCADA.

The documented design scope includes:

  • Redundant control with a secondary system.
  • Modbus integration with smart ACBs and MCCBs.
  • Power-system monitoring and control through SCADA.
  • Commissioning documentation for testing and site delivery.

Design and testing stage

This project profile covers the design and documentation stage. At that stage, factory acceptance testing of the standby-power switchboard was planned before shipment to the hospital.

Talk to Tim about control-system design.

Let’s work it through

What does your power
system need to do?

A new installation, an upgrade or a system that needs a second look. Start with a conversation.

Talk about your project